A bottleneck is a resource or stage that limits the capacity of a process. Work cannot move through the whole system faster than its effective constraint permits. The constraint may be a machine, a specialist employee, an approval step or another scarce resource. It concerns the flow of completed output, rather than whichever employee looks busiest.
In a simple sequence, increasing capacity at a non-bottleneck stage does not necessarily increase final output. It may only create a larger queue before the constrained stage. Improving the bottleneck can increase capacity, but another stage may then become the new constraint. Actual throughput also depends on available work, materials, reliability and demand.
For a small business owner in England, the practical task is to map the process, measure useful capacity and observe where work waits. The owner can then consider protecting the constrained resource from interruptions, reducing rework or adding suitable capacity. An expensive new machine is not justified merely because it runs faster if the limiting step is elsewhere or customers will not buy the extra output.
Worked example, using invented hourly capacities for an English workshop. Every job passes through cutting, assembly and packing in that order. Assume comparable jobs, sufficient demand and materials, no losses and no other constraints.
| Particulars | Working / amount |
|---|---|
| Cutting capacity | 12 jobs per hour |
| Assembly capacity | 8 jobs per hour |
| Packing capacity | 10 jobs per hour |
| Maximum whole-process capacity | Minimum of 12, 8 and 10 = 8 jobs per hour |
Assembly is the bottleneck. Raising cutting capacity alone leaves final capacity at eight jobs per hour under these assumptions.