Float time is the amount of scheduling flexibility available to an activity in a project network. Total float measures how far an activity can be delayed without delaying the planned project finish, under the network's assumptions. It is different from the activity's duration and from cash held as a float.
Total float can be calculated as latest start minus earliest start, or latest finish minus earliest finish. These times come from the sequence of activities and their estimated durations. Free float is narrower: it measures delay possible without delaying the earliest start of a following activity. In a simple network, critical-path activities have no total float.
For a small business owner in England, float helps decide where scarce people or equipment can be moved temporarily. It is not spare time that every activity can consume independently. A delay can use flexibility shared along a sequence, and altered durations or dependencies require the network to be recalculated. Resource limits can also make the practical schedule tighter than the network first suggests.
Worked example, using invented times: an English business schedules a task with earliest start at day 2 and latest start at day 5. Assume the network is valid, resources are available and project completion must stay unchanged.
| Particulars | Working / amount |
|---|---|
| Earliest start | Day 2 |
| Latest start | Day 5 |
| Total float | 5 − 2 = 3 days |
The task can start up to three days later under these assumptions without moving project completion. That does not mean every later task gains three extra days as well.