Latest finish time is the latest point at which an activity can finish without delaying the planned completion of a project, assuming the rest of the schedule proceeds as modelled. In critical path analysis, it is found by working backwards from the project's completion time through its dependencies.
For an activity, latest finish equals the earliest of the latest start times of its immediate successors. Latest start is latest finish less the activity's duration. In activity-on-arrow diagrams, a node's latest time is found by subtracting each following activity's duration from its end-node latest time and taking the lowest result. Total float for an activity is its latest finish less its earliest start less its duration.
For a small business owner in England, use these times to understand where delay can be absorbed, not as a reason to postpone every task. Shared staff, uncertain durations and changing customer requirements may make the original network unrealistic. Delays that use available float can leave less protection for later problems. Review the schedule when activities or dependencies change.
Worked example, using invented figures: an English shop refit includes a painting activity that takes three days. Its successors must start by day eight and day ten respectively. Assume the dependencies and durations are reliable.
| Particulars | Working / amount |
|---|---|
| Latest starts of successors | Day 8 and day 10 |
| Painting latest finish | Earlier requirement: day 8 |
| Painting latest start | 8 − 3 = day 5 |
Finishing on day ten would satisfy only the later successor and would delay the one that must start by day eight.