Net present value, or NPV, is the present value of a project's expected future net cash flows less its investment cost. It discounts future cash because money received later is worth less today at the chosen required return. The method helps compare an investment with the return required for committing funds and taking risk.
For each period, divide the net cash flow by (1 + the discount rate) raised to the number of periods from today. Add the present values, including any initial outflow. A positive NPV suggests the project exceeds the required return on the assumptions used; a negative NPV suggests it falls short. Forecast cash is not guaranteed.
Use relevant future cash flows rather than accounting profit or money already spent. Timing, tax, working capital, residual value and consistency between inflation assumptions and the discount rate can matter. A small business must consider affordability and risk even where NPV is positive.
Invented worked example: a project costs £10,000 now and returns a single net £12,100 after two years, with no other cash flows. The assumed annual discount rate is 10%. All figures are teaching assumptions, not an investment recommendation.
| Discounted-cash-flow calculation | Result |
|---|---|
| Present value: £12,100 ÷ (1.10 × 1.10) | £10,000 |
| Less: investment paid now | (£10,000) |
| NPV: £10,000 − £10,000 | £0 |
A zero NPV means the project exactly meets the assumed required return. It does not mean undiscounted receipts equal the original cash cost, or that the project has no risk.