An overhead absorption rate is a rate used to charge indirect costs to products, jobs or services through a chosen activity base. A predetermined rate is calculated as budgeted overhead divided by budgeted activity. It helps assign a share of costs that cannot be traced directly to an individual unit.
The base might be machine hours, direct labour hours or units, depending on the work and costing system. State it clearly: a rate per machine hour is not a rate per finished product. A business may use separate rates for different departments where their costs and activities differ substantially.
The method gives a consistent costing basis, but it is an allocation model rather than proof that each job caused precisely that amount of overhead. Actual activity and spending can differ from budget, producing over- or under-absorption. Owners should review the choice of base and the assumptions before relying on the figures for pricing, capacity or product decisions.
Invented worked example: a workshop budgets £24,000 of production overhead and 6,000 machine hours for the year. A job is expected to use three machine hours. These are teaching assumptions. The rate allocates overhead to the job; direct materials and direct labour would still need to be considered separately when calculating its total cost.
| Calculation | Result |
|---|---|
| Budgeted production overhead | £24,000 |
| Budgeted machine hours | 6,000 hours |
| Rate: £24,000 ÷ 6,000 | £4 per machine hour |
| Job overhead: 3 hours × £4 | £12 |