Standard costing is a control method that sets expected costs for a product, service or activity and compares them with actual results. A standard may specify quantities of materials, labour time and the prices or rates expected. Differences are called variances. The aim is to understand why results departed from the plan and decide whether action is needed.
Compare actual costs with the standard cost allowed for the actual output, rather than automatically using the original budget for a different volume. Price or rate differences and quantity or efficiency differences can then be examined. A favourable cost variance means cost is below the relevant standard; it does not necessarily mean the business has performed better overall.
In this invented worked example, a workshop sets a material standard of 2 kg at £3 per kg for each unit. For 100 units actually made, standard material cost is £600. Actual material cost is £660, giving a £60 adverse total material cost variance. Further analysis is needed to distinguish a price change from extra material usage.
For a small-business owner, use standards that reflect a clear operating assumption and review them when conditions change. Investigate significant differences with the people doing the work. Cheaper material may create waste, while extra training may raise short-term cost and improve later output. Standards support questions and decisions; they should not become automatic blame or a reason to pursue a favourable number at the expense of quality.
| Calculation | £ |
|---|---|
| Standard cost: 100 units × 2 kg × £3 | 600 |
| Actual material cost | 660 |
| Adverse variance: £660 − £600 | 60 |