Under-absorption occurs when the overhead charged to output is less than the actual overhead incurred for the period. Under absorption costing, a business commonly uses a predetermined overhead absorption rate to assign production overhead to products. The rate is based on budgeted overhead and budgeted activity, so the amount assigned will not necessarily match the eventual actual cost.
The calculation compares actual overhead incurred with overhead absorbed using the chosen activity base. Under-absorption can arise because actual overhead exceeds its budget, because the relevant activity is lower than budgeted, or through a combination of changes. It does not automatically mean that employees worked inefficiently. The explanation depends on how the rate was set and how costs and activity actually behaved.
In this invented worked example, a workshop budgets fixed production overhead of £12,000 and 3,000 machine hours. Its absorption rate is £4 per machine hour. Actual activity is 2,500 machine hours and actual fixed overhead is £12,000. Only £10,000 is absorbed, leaving £2,000 under-absorbed. The example deliberately holds expenditure constant to isolate the effect of lower activity; it does not establish why that activity fell.
For a small-business owner, investigate whether demand, downtime, capacity planning or expenditure explains the difference before changing product prices or blaming staff. An absorption adjustment affects reported profit under the relevant accounting treatment, but the difference is not itself a separate cash payment. For students, show the rate, the activity applied and the comparison with actual overhead. Do not compare absorbed overhead only with budgeted expenditure when actual expenditure differs, or confuse under-absorption with the separate question of whether the business has made a loss.
| Invented fixed-overhead example | Calculation |
|---|---|
| Budgeted overhead / machine hours | £12,000 ÷ 3,000 |
| Absorption rate | £4 per machine hour |
| Overhead absorbed | 2,500 × £4 = £10,000 |
| Actual overhead less absorbed | £12,000 − £10,000 |
| Under-absorbed overhead | £2,000 |