Absorption costing assigns production overheads to units of output as well as their direct production costs. A product's production cost therefore includes an appropriate share of costs such as factory rent and supervision. Those overheads support production even though they cannot be traced directly to each individual unit.
An overhead absorption rate is calculated using a chosen basis, such as machine hours or labour hours. The rate is then applied to each product's use of that basis. The choice matters: a simple rate can give a misleading picture when products consume support activities in very different proportions. Absorption costing estimates cost; it does not establish the price customers will pay.
For a small workshop, the method helps prevent the owner from treating materials and direct labour as the whole production cost. Selling and administration costs still need consideration when judging overall profitability. If actual overheads or activity differ from the budget used to set the rate, overheads can be under- or over-absorbed.
Worked example, using invented figures for a workshop. All overheads in this example are production overheads, and the selected basis is machine hours.
| Particulars | Working / amount |
|---|---|
| Budgeted production overheads | £12,000 |
| Budgeted machine hours | 3,000 |
| Overhead absorption rate | £12,000 ÷ 3,000 = £4 per hour |
| Machine hours per unit | 2 |
| Overheads absorbed per unit | 2 × £4 = £8 |
| Direct materials per unit | £18 |
| Direct labour per unit | £14 |
| Production cost per unit | £18 + £14 + £8 = £40 |
The £40 includes the unit's allocated production overhead. It is not a selling price or a promise that the workshop will recover all its costs.