The critical path is the sequence of dependent project activities whose combined duration determines the earliest possible completion of the planned work. In a simple network, it is the longest-duration path from start to finish. It is not necessarily the path containing the most tasks or the task the owner regards as most important.
An activity on the critical path has no total float in the standard unconstrained calculation: delaying it delays the project unless another change recovers time. Other activities can still cause delay if they use up their available float. A project may have more than one critical path, and the critical path can change when durations or dependencies change.
For a small business owner in England, identifying the critical path helps focus attention on handovers and tasks that govern a launch, move or installation. The calculation relies on credible estimates and dependencies. It does not by itself prove that the same people or equipment can do every parallel task. Resource constraints and uncertainty still need separate attention.
Worked example, using invented working-day durations for an English shop refit: task A takes two days. Tasks B and C can both start after A and take five days and three days respectively. Task D takes one day and starts only when both B and C are complete. Assume resources allow B and C to run in parallel.
| Particulars | Working / amount |
|---|---|
| Path A–B–D | 2 + 5 + 1 = 8 working days |
| Path A–C–D | 2 + 3 + 1 = 6 working days |
| Critical path and duration | A–B–D; 8 working days |
The shorter path does not allow the refit to finish in six days, because D must also wait for B.