Free float is the amount of time a project activity can be delayed without delaying the earliest start of any activity immediately following it. It measures local scheduling flexibility within a network. In this project-management sense, float is time, not cash or shares available for trading on a stock market.
For an activity with several immediate successors, use the earliest of their earliest start times, less the activity's earliest finish. Total float is different: it measures delay possible without delaying the planned project completion. An activity can therefore have total float while having no free float, because delaying it would move a successor even though the whole project could still finish on time.
For a small business owner in England, free float can help identify which tasks can move without immediately disrupting another team's planned start. Check the dependencies and durations before using it. A network describes assumptions, not guaranteed spare capacity, and shared people or equipment can impose further limits. Recalculate when the sequence changes rather than treating the original float as permanently available.
Worked example, using invented times: an English business schedules a task to finish at day 6. Its immediate successors have earliest starts at day 8 and day 10. Assume no additional dependency lags and that the network and resources remain unchanged.
| Particulars | Working / amount |
|---|---|
| Earliest finish of task | Day 6 |
| Earliest successor start | Earlier of day 8 and day 10 = day 8 |
| Free float | 8 − 6 = 2 days |
The task can use two days without moving either successor's earliest start under these assumptions. This is not a calculation of the whole project's total float.