Incremental budgeting prepares a new budget by taking an existing budget or actual result as its starting point and adjusting it for expected changes. Those changes might include prices, sales volumes, staffing or planned activities. It is a method of building the budget, not a rule that every spending line must increase.
The approach is relatively simple and can suit stable operations where the previous period remains a useful guide. Its weakness is that it can carry forward waste, outdated assumptions and budget slack. Managers may defend existing allocations rather than question whether the activity still deserves funding. An adjustment for inflation alone does not establish what the business actually needs.
For a small business owner in England, separate changes in price from changes in activity and identify exceptional items in the starting figures. Check whether the budget reflects current plans, contracts and capacity. Compare it with available cash and test the assumptions. Zero-based budgeting starts by requiring expenditure to be justified afresh; incremental budgeting normally questions the changes more than the whole existing cost base.
Worked example, using invented figures: an English business starts with a comparable annual supplies cost of £20,000. It expects prices to rise by 5%, with usage unchanged. Assume no exceptional items or other changes.
| Particulars | Working / amount |
|---|---|
| Starting cost | £20,000 |
| Expected price increase | £20,000 × 5% = £1,000 |
| New budget | £20,000 + £1,000 = £21,000 |
The £21,000 follows from the stated assumptions. It is not evidence that the previous spending was efficient or that the supplier has quoted that increase.