Labour efficiency variance measures the cost effect of using more or fewer direct labour hours than the standard allows for the actual output produced. It values the time difference at the standard hourly rate, so that a change in pay does not distort the measure of time efficiency.
Calculate standard hours for actual output, subtract actual hours worked, then multiply by the standard rate. Under this convention, a positive result is favourable and a negative result is adverse. Use actual output, not the original budgeted quantity. If idle time is analysed separately, distinguish hours worked from hours paid.
For a small business owner in England, investigate the process rather than automatically blaming employees. Training, material quality, equipment problems or an unrealistic standard can affect the time needed. A favourable result can hide rushed work or defects, while more expensive skilled workers may save time. Read efficiency and rate variances together and check quality as well as cost.
Worked example, using invented figures: an English manufacturer makes 800 units. The standard allows half an hour per unit at £18 an hour. Actual work takes 420 hours. Assume no idle time and no change in output quality.
| Particulars | Working / amount |
|---|---|
| Standard hours for output | 800 × 0.5 = 400 hours |
| Extra hours used | 420 − 400 = 20 hours |
| Labour efficiency variance | 20 × £18 = £360 adverse |
The £360 is a standard-cost measure of extra time, not a separate bill or proof of its cause.