Labour rate variance measures the cost effect of paying a different hourly rate from the standard rate. It compares actual labour cost with what the actual hours paid would have cost at the standard rate. It isolates the pay-rate effect rather than the effect of taking more or fewer hours.
One calculation is actual hours paid multiplied by the standard rate, minus actual labour cost. Equivalently, multiply actual hours paid by the standard rate less the actual rate. Under this convention, a positive result is favourable and a negative result is adverse. When paid idle time exists, do not silently substitute hours worked for hours paid.
For a small business owner in England, causes may include overtime premiums, a different mix of staff or a pay change not reflected in the standard. A lower rate is not automatically a better outcome if it brings poorer quality or more hours of work. Review the rate variance alongside efficiency, working arrangements and the reasonableness of the standard. It is an explanation of a cost difference, not an instruction to reduce pay.
Worked example, using invented figures: an English producer pays for 300 hours at £19 an hour against a standard of £18. Assume all paid hours are worked and there is no idle time.
| Particulars | Working / amount |
|---|---|
| Actual labour cost | 300 × £19 = £5,700 |
| Hours at standard rate | 300 × £18 = £5,400 |
| Labour rate variance | £5,400 − £5,700 = £300 adverse |
The adverse £300 concerns the rate paid. Any difference between actual hours and standard hours for output belongs in the efficiency analysis.