Network analysis

Network analysis is a project-planning technique that maps activities, their durations and the order in which they must happen. It helps identify which work can run in parallel, the shortest possible project duration under the assumptions and the activities whose delay would delay completion.

The critical path is the longest-duration route through the network. It sets the minimum completion time, rather than the fastest-looking individual task. Critical activities have no total float in the basic model. Total float is the time an activity can be delayed without delaying the project finish; it can be calculated as latest finish minus earliest start minus duration.

Invented worked example: a shop refit starts with planning activity A, lasting two days. After A, fitting activity B takes four days and signage activity C takes three days; they run in parallel. Opening preparation D takes one day and must wait for both. These durations are teaching assumptions. The table compares the two routes.

The plan takes seven days. C has one day of float if the other assumptions hold. Shortening C alone does not shorten the project. Estimates, staff availability and dependencies need review: a network is a planning aid, not a promise that resources will be available or tasks will finish on time.

Route and calculation Duration
A → B → D: 2 + 4 + 1 7 days
A → C → D: 2 + 3 + 1 6 days
Critical path: A → B → D 7 days

By Business Robot

Archives

Questions and Answers (0) Researched Thinking (0) Data Protection (0) News (0)

Archive by tags

All (1083) Accounts & records (6) Branding & trade marks (2) Business borrowing (5) Business continuity (2) Business expenses (7) Business premises (3) Business rates (1) Business structure (6) Capital Gains Tax (5) Cash flow (6) Commercial contracts (7) Company cars (3) Consumer law (5) Corporation Tax (2) Customer payments (1) Data protection (4) Directors & Companies House (5) Economy & policy (3) Employing people (16) Getting paid (6) glossary (997) Health & safety (2) Income Tax & Self Assessment (10) Insolvency (3) Insurance (4) Making Tax Digital (4) Marketing & sales (5) National Insurance (7) Owner pay & dividends (2) Pensions (4) Pricing & profitability (10) Selling a business (3) Technology & AI (4) VAT (8)

Ask a Question