PERT stands for Programme Evaluation and Review Technique. It is a project-planning method that maps the activities needed to complete a project, the dependencies between them and uncertainty in how long they may take. It is useful when a single fixed duration would hide important risk.
Traditional PERT uses three time estimates for an activity: optimistic, most likely and pessimistic. A commonly used expected duration is (optimistic + 4 × most likely + pessimistic) ÷ 6. This gives the most likely estimate greater weight. The network then helps identify the critical path, the longest dependent sequence that determines the planned project duration.
The following worked example uses invented estimates for preparing a small business's online booking system. All estimates are in working days for the same activity.
| Estimate or calculation | Working days |
|---|---|
| Optimistic estimate | 2 |
| Most likely estimate | 5 |
| Pessimistic estimate | 8 |
| Weighted total: 2 + (4 × 5) + 8 | 30 |
| Expected duration: 30 ÷ 6 | 5 |
An expected duration is not a guaranteed completion time. Delays, shared staff and changing dependencies can alter the result. Estimate each activity consistently and review the network as work progresses. Do not add the durations of parallel activities as though all tasks happen one after another. PERT supports judgement about scheduling; it does not make weak estimates reliable merely by applying a formula.